NVR Logo
Building to beat the rain
Construction workers at the First Street bridge are pouring concrete for the piers while project managers and engineers keep an eye on the weather. Jorgen Gulliksen/Register | Buy photos
First Street bridge crews hustle to finish before winter hits
Tuesday, October 28, 2008
Save and Share Share
The city of Napa Public Works Department is of two minds about having a long, wet winter.

Heavy rains would help to fill local reservoirs, but if the rains come early they could set back construction of the First Street bridge over the Napa River.
“We’re keeping our fingers crossed for a dry November-December,” said Jason Holley, the engineer who oversees the project for the city. “It’s no fun building anything in the rain.”

If the rains kicked off fast and furious, the $15 million project might have to shut down for the winter, wrecking plans to reopen First to traffic in August, he said.
Fortunately, the California Department of Fish and Game has twice extended the deadline for completing the construction of the bridge foundation in the middle of the river, Holley said Monday.

The original deadline of Oct. 15 was moved to Oct. 31, and now to Nov. 21, assuming that Mother Nature doesn’t go on a rampage before then, Holley said.
Showers are predicted for this weekend, but they shouldn’t do more than knock the dust down, Holley said. The general contractor, American Civil Constructors, should be able to continue working full-bore.

For nearly a month, the contractor has been working seven days a week, with double shifts most days. When critical repairs had to be made a week ago to repair a leaking cofferdam, construction lasted all night.

Neighbors have complained about the noise and the glare from banks of lights, Holley said.

Except for the cofferdam emergency, construction stops at 9 p. m., with the contractor trying to confine the noisiest work to daylight hours, Holley said.

Monday was an important milestone in the rush to build two supporting piers in the riverbed, Holley said. Pumpers on each bank delivered 340 cubic yards of concrete to complete the construction of the eastern pier wall and lay the foundation for the western support.

The pier foundation starts 28 feet below water and will rise 20 feet above it.

Within a month, the western pier should also be completed, allowing workers to yank the wall of steel that holds back the water that rises and falls with the tides, he said.

Construction ran into difficulties in the early stages, requiring the Fish and Game extensions, Holley said. “We had difficulties excavating some material,” he said. “There is a learning curve to everything.”

Doug Silverwood, American Civil Constructors’ project manager, said he wasn’t allowed to talk about job issues. “It’s going well. We’re still on schedule to finish up on time,” he said.

On days when two shifts of workers are forming rebar for the foundations, the job site has as many as 50 workers, Silverwood said.

Working in a tidal river poses more challenges than building in a steady stream, Silverwood said. With the tide rising and falling as much as 10 feet, “it creates pressures on things,” he said.

The piers and abutments of the First Street bridge will be a lot like those in other bridges, Silverwood said. What will distinguish this span will be the ribbons of glass in the sidewalks and lighting built into obelisks, he said. This span will have “architectural flavor,” he said.
5 comment(s)

jwk wrote on Oct 28, 2008 12:35 AM:

" And the City and the builders didn't plan for rain? in Napa?? Sounds like a pretty bridge for the Ritz Hotel patron's BUT why was this project put ahead of The Berens St. Bridge/Napa Creek project? I think I just answered my own question. To Heck with you Locals and Business owners in that area. The tourists are far more important. We will flood again in The Creek area for sure. Maybe we can all have The City of Napa and The Flood project people move our stuff up on the new bridge this next one?? "

auntielmo wrote on Oct 28, 2008 11:45 AM:

" "Neighbors have complained about the noise and the glare from banks of lights, Holley said" .. This comment is hilarious.

Being a residence in the middle of the construction zone, we have complained about more than just noise & the lights. Try having a generator running 24/7 outside your bedroom window while you are trying to sleep. And yet we are told its meeting the noise level etc. Or have lights on all night long for no reason (on the west bank shining onto the east bank) right into your bedroom window. Or having a broken up sidewalk that several of us have taken a fall, & yet its still broken after months of emails & responses saying it will be done.

With the construction of this bridge being Monday - Sunday 7am - 9pm, we get no rest what so ever. Want to have a quiet weekend, bbq, birthday party or take a nap on your day off. Forget about it. Because you cant.

I find out more information about the status of the bridge construction from the NVR than from the city of Napa. "

winghunter wrote on Oct 28, 2008 12:06 PM:

" JWK... I empathize with you, living next to a creek that continually floods would get very old. I remember when I bought a place next to the railroad tracks and after repeated calls to Southern Pacific they would not move the tracks. Don't get me started on the place I bought next to the airport, those planes flew all hours of the day and night!!! "

MarshaMarsha wrote on Oct 28, 2008 1:29 PM:

" The project engineer is hoping for a dry Nov-Dec??? Seriously???

Citizens of Napa can survive without the bridge for a little longer, but rain is required for basic life.

I'm sorry, Mr. Holley, if it's "no fun to build anything in the rain", but I think your priorities are a bit skewed. "

jwk wrote on Oct 28, 2008 10:09 PM:

" you are quite the nice guy winghunter. The thing is the creek doesn't need to flood and it can and should of been fixed by now. Way Before the Tourist Bridges, Oxbow, Hatt Flood Wall and Veterns Park projects that have never flooded. You should run for City Council!! I bet you'd get alot of votes except for all the residents and business's on Main st. , Brown st, Vallejo st, Clinton st. Arroyo dr, Pearl st. and Yajome st. to just pick up and move. Why don't they just make everybody near the river move too?? "

Comment Guidelines
The goal of the story comments section at NapaValleyRegister.com is to have an open, thought-provoking, civil community forum for all issues.
What gets your comment posted?
• Staying on topic
• Keeping your comment to 300 words or less
• Avoiding name-calling
• Addressing your comments to the message rather than the messenger
What gets your comment deleted?
• Personal attacks
• Derogatory remarks
• Name-calling of any sort
• Going off-topic
• Hate speech
• Racially-insensitive comments
• Implying guilt of a subject in a crime story before there is a court verdict
• Posting e-mail addresses
• Posting comments of a commercial nature
• POSTING WITH ALL CAPITAL LETTERS
• Linking multiple comments together with "to be continued..." to get around the 300 word limit.
The fine print
- Comments are either approved or denied. We do not edit comments.
- You are welcome to modify and resubmit a denied comment.
- Comments may take several hours to be posted.
- Comments posted are those of the writer, and do not necessarily reflect the opinion of NapaValleyRegister.com, its employees or its parent company.
- Do you have information on a story? Please go to our virtual newsroom to send us a news tip.
- If you feel a posted comment has violated our guidelines, please contact online@napanews.com or add a comment indicating you have an issue and our moderators will review the comment in question.
Search:
Web Search Powered
By Yahoo! Search
Napa Valley Register on Facebook
Copyright © 2009 Napa Valley Publishing, a member of Lee Enterprises, Inc.
Terms of Use | Privacy Policy